Investigation of Circuit Breaker Switching Transients for Shunt Capacitor Using Matlab/Simulink

Authors

  • Seema S. Kalwaghe  M.E Electrical Engineering (EPS) Department, G. H Raisoni College of Engineering, Amravati, SGBAU University, Amravtai, Maharashtra, India
  • Prof. Mukund R. Salodkar   M.E Electrical Engineering (EPS) Department, G. H Raisoni College of Engineering, Amravati, SGBAU University, Amravtai, Maharashtra, India

Keywords:

Inrush Current, Capacitor Bank, Shunt Capacitor Switching.

Abstract

It is common practice to install shunt capacitors to improve the power factor and voltage profile at all voltage levels in the power system. Almost all type of load including domestic user’s appliances are inductive. Due to low water level agricultural load are also increasing. All these conditions lead to poor power factor and large amount of reactive power flows through the transmission line and voltage drop occurs. Hence, in several areas low voltage pockets are created. To improve this low power factor, adequate compensation is to be provided at load end point. Due to increasing load/consumers it is very difficult to insist every consumer to provide compensating device. Ultimately power transmission companies have decided to provide the capacitor bank at the feeding substation at various voltage levels such as 11KV, 33KV and EHV levels also. And now a day it is well accepted practice to install a capacitor bank at the feeding substation for improving the power factor of the system. The major problem with the capacitor bank is the interrupter failure i.e. the failure of circuit breaker employed for its switching. It is reported by power distribution and transmission companies that breaker failure occurs before its specified number of operation. In order to understand this problem, I thought of taking a topic of dissertation work, which relates to the failure of circuit breaker employed for capacitor switching.

References

  1. Gustavo Brunello, Dr. Bogdan Kasztenny, Craig Wester, Shunt Capacitor bank Fundamentals and Protections,” 2003 conference for Protective Relay Engineers-Taxas A&M University April 8-10,2003, IEEE Guide for the Protection capacitors Banks.
  2. Florin korner, Manfred Lindmayer, Michael Kurrat (Institute for Hochspannungstechnik and Elektriche Energieanlagen, Technische Universitat Braunschweig Germany), Dietmar Gentsch, ABBA Gcalor Emag Mittels Pannungsprodukte, oberhausenestrabe 33,40472 Ratingen, Germany. -Synthetic test of Capacitive current switching using a test vessel”,1_4244_0192_5/06/$20.00 2006IEEE.
  3. Lutz GEBHARDT, Bernhard RICHIER?? ABB_Switzerland -surge arrester application of MV-capacitor banks to mitigate problems of switching restrikes”,19thInternational conference on electricity distribution Vienna,21-24 May -2007.
  4. Ying-Yi Hong and - Yaunchen. -Locating switch capacitor using a wavelet transform and hybrid principle component analysis network”, 0885-8977/$25.00 2007 IEEE.IEEE transactions on power delivery.vol.22. No-2, April_2007.
  5. Joe Rostran, P.E. 3/12/2007 Southern states LLC, Hampton, Ga. Editor: David Childress 8/12/07, southern states LLC Hampton, GA -Analysis of example capacitor bank switching solution and recommendations for revision”.
  6. Mohd Shamir Ramli, M. Eng. thesis, QUT, 2008 on -Investigation of circuit breaker switching transients for shunt reactors and shunt capacitors”, Queensland university of technology.
  7. S.J. Kulas, Faculty of Electrical Engineering, Warsaw university of technology GG130, PL. Politechniki_1,00_662 Warsaw, Poland. -Capacitor switching techniques”, International conference on renewable energies and power quality (ICREPQ ‘09), Valenicia(Spain),15th? -17th? April,2009.
  8. Shehab Abdul wadood Ali, Department of Physics college of saber, university of Aden, Adenyemen -Capacitor banks switching transients in power system”, CSC Canada Energy Science and Technology, vol-2, NO.2,2011.
  9. Gopal Gajjar, A. M. Kulkarni and S. A. Soman. Department of Electrical Engineering, Indian institute of technology Powai, Bombay, Mumbai(India), Paper submitted to the International conference on Power Systems (IPST 2013) in Vancouver, Canada Jully 18-20,2013. -Interaction of Capacitor Bank Inrush Current Limiting Reactor and Medium Voltage Vaccum Circuit Breakers”.
  10. Salil S. Sabade, Himanshu J. Bahirat, Dr. Bruce A. Mork, Department of Electrical and Computer Engineering, Michigan Technological University, Houghton, MI 49931.Mythili Chaganti, Xcel Energy Inc.414 Nicollet Mall, Minneapolis, MN55401 on -Shunt Reactor Switching Transients at High Compensation Levels”.
  11. Shunt Capacitor Bank Switching Transients A Tutorial and case study”, carried out by Govind Gopalkumar, Huihuayan, Dr. Bruchs A. Mork of Michigan Technological University Houghtan, MI 49931 and Kalyan K.? Mustabhi, Northern states Power Company, Minneapolis, MN-55401.
  12. Power Systems Capacitors, Ramswamy Natarajan.

Downloads

Published

2017-10-31

Issue

Section

Research Articles

How to Cite

[1]
Seema S. Kalwaghe, Prof. Mukund R. Salodkar , " Investigation of Circuit Breaker Switching Transients for Shunt Capacitor Using Matlab/Simulink , International Journal of Scientific Research in Science and Technology(IJSRST), Online ISSN : 2395-602X, Print ISSN : 2395-6011, Volume 3, Issue 7, pp.756-759, September-October-2017.